2026 Greenbelt Improvement Project

The City of Boise’s Parks and Recreation Department has budgeted for Boise River Greenbelt projects in fiscal year 2026 to repair and replace sections of the Greenbelt that are in poor condition. One section of pathway identified for updates is located near Wood Duck Island along E. Parkriver Dr. from S. Temperance Way to E. Rivernest Court. The project will result in significant improvements of the existing Greenbelt pathway at Wood Duck Island and connection to Barber Park. This project will be constructed in 2026.

Greenbelt Construction November 2026
Wood Duck Island Greenbelt Construction Project - November 2026

November 2026 Construction Update

The contractor has completed work on the two westernmost sections of Boise River Greenbelt outlined in the project scope, which are now open for use. Demolition is underway on the middle portion of pathway, and this work is expected to progress more quickly as the project moves forward and early construction questions have been resolved. Please stay out of any fenced or closed areas for your own safety. The project remains on schedule with completion expected by the end of 2026. Thank you for your continued patience and cooperation as crews complete these important improvements.

Granite Construction won the bid for this Greenbelt improvement project. Site mobilization began in early August and the contractor started work on the west end of the Greenbelt pathway slated for improvements. Work is then scheduled to shift to the east end near Barber Park with the goal of completion by the end of the calendar year (2026). Boise Parks and Recreation will continue to share updates as they are available.

This section of pathway was selected as high priority for replacement due to current poor conditions. Some of the paths are cracked, others have damage due to roots or degrading subgrade. The existing asphalt paths will be replaced with concrete, creating a smooth surface. Concrete lasts much longer than asphalt and is less susceptible to tree root damage. All of the existing benches, trash cans and bollards will also be updated.

The department’s priority is to continue to repair and or replace sections of the Boise River Greenbelt on an annual basis, as funding allows.

Wood Duck Island Phase 1 Project Area

Our team realizes the Greenbelt is heavily used as a transportation corridor and for recreational purposes. The department will make every effort to work with contractors to complete these projects efficiently. Detours will be established and signed for all projects, and we will update our website to provide information throughout construction.

We apologize for the temporary inconvenience during repair and replacement but in the long run, the department is confident this work will improve the longevity of the path and create a better user experience for everyone.

Questions?

Email
Call: 208-608-7600, option 1
TTY: 711


Project completion estimates are subject to change due to volatility in the construction industry. Current challenges include material availability, rising costs, supply chain disruptions, staffing shortages and more. Boise Parks and Recreation will update project timelines as needed if delays occur.

Message Sent Successfully!

Message Failed To Send.

Send a Message to Parks and Rec

For other after hours park related emergencies (i.e. irrigation issues, restrooms), please call (208) 489-6640.