Demolition/Deconstruction

Boise skyline with construction

What is the Moving, Deconstruction or Demolition of Buildings Code?

This chapter of City Code provides minimum standards and requirements for contractors, developers and owners when moving, deconstructing, or demolishing buildings and structures.

This code includes provisions such as required permits, bonds, insurance, notifications, any barriers needed, debris removal, and recycle or reuse provisions.

The city has implemented a Deconstruction and Demolition Material and Waste Management Plan to provide contractors with a guide to identify materials diverted from the landfill as waste to be recycled or reused.

What is the Recycle/Reuse Process for Deconstruction or Demolition Permits?

  1. Unless previously approved through Design Review in Planning, the owner, owner representative or contractor must obtain approval through Planning and Zoning first, where applicable, through a Planning Project application.
  2. Submit the appropriate building permit application through the City of Boise Permitting and Licensing page. The application includes a Deconstruction and Demolition Material and Waste Management Plan – Estimation Proposal section and will prompt you to upload photos of the building and available materials for recycling or reuse. The City will send an email with a link to the application, which includes your uploaded photos notifying reuse/recycle companies of available materials.
  3. Allow up to five (5) business days for response of interest in any materials from Reuse Companies. If interest, coordinate schedule and timeframe for salvage and pick-up of materials.
  4. Building Inspector determines amount of bond to be posted and in some cases, a site visit may occur.
  5. The Public Works Sewer Plug reviewer determines if a Sewer Plug is required.
  6. The permit desk will request remaining documentation required to proceed to issuance.
  7. Building permit review completed, bond posted and permit, along with other associated permits (sewer cap, erosion and sediment control) issued.
  8. Work to salvage recycle/reuse materials occurs. All appliances, solid metals accepted at local metal recyclers and woody yard debris 10 cubic yards or greater are required to be recycled at an area Recycling Company.
  9. Any other desired recycle/reuse materials can be further salvaged by the contractor or are to be coordinated with Reuse Companies when materials are requested. Adequate time shall be provided for the contractor, or designated person, to carefully remove the requested material items, haul and/or set aside the materials for pick-up prior to project work completion. (Note: Early surface level type work to salvage materials for recycle or reuse may be acceptable to occur prior to permit issuance.)
  10. The remainder of the project work is completed.
  11. After project completion, submit a Deconstruction and Demolition Material and Waste Management Plan – Actual Diversion Report (450 A Form), including copies of recycling, reuse and landfill receipts, weight tickets, hauler receipts or other diversion documentation. Documentation can be sent via email to permits@cityofboise.org.
  12. The contractor schedules a final inspection through the City of Boise Building Division. The building official, or designee, may require independent third-party audit and/or verification where deemed necessary.
  13. Once the final inspection has passed, contact the City of Boise Permit Desk to request the bond be released.
  14. The City Building Division reviews and approves the documentation provided and returns the bond.
wood pallets

What are the Benefits of Recycling and Reuse?

  • Aligns with City of Boise initiatives on sustainability.
  • Diverts and reduces amount of materials in landfill as waste.
  • Conserves resources through recycling of materials.
  • Generates reusable materials as marketable products from salvage.
  • A material and waste management plan documents materials that are being deposited in landfills as waste and materials diverted for recycle or reuse. Over time, this documentation can help determine materials or markets that are viable and working, areas that are not so viable, or even emerging markets that are developing.
  • Tax deduction for donations of reuse materials to certain organizations.

Note: Any hazardous materials (i.e. asbestos, lead paint, mercury, refrigerants) that may exist on projects are to be abated in accordance with Environmental Protection Agency (EPA) requirements, where applicable, or other state or local requirements.