Background
The City of Boise Pathways Master Plan identified the pathway connecting the east end of Grove Street at 3rd Street to Broadway Avenue as a near-term, high-priority, medium-feasibility pathway corridor in 2022.
The Capital City Development Corporation (CCDC) Grove Street Redevelopment Strategy Vision Report also identified a need for a multi-use pathway connection from the intersection of Grove Street and 3rd Street to the pedestrian crossing on Broadway, near Dona Larsen Park. Through CCDC’s commitment to strategic investments that improve access and mobility in our community, construction of the Grove Street Pathway began in December 2024 and was completed in late 2025. The total cost of the project was $3,946,402. The project was funded by CCDC and transferred to the City of Boise’s Parks and Recreation Department for ongoing management