Broadway - Federal Way Pathway

Project Background

Project location: Near the Federal Way and Broadway Avenue interchange

Project background: This project began as a request for a bike and pedestrian connection between Federal Way and Broadway Avenue from the South Boise Village Neighborhood Association in 2018. A pre-concept report was developed in 2020 through COMPASS’s Project Development Program. The project was awarded federal funds in 2022 for design and construction.

View Larger Concept Map

Conceptual site map of Broadway-Federal Way Pathway 2026
Conceptual site map of Broadway-Federal Way Pathway 2026

Impacts

This project will:

  • Provide new connections to several nearby schools, parks, commercial areas, and employment,
  • Close a 2.2-mile gap in the bike and pedestrian network,
  • Provide a continuous connection from the Federal Way Pathway to the Greenbelt,
  • Provide 1,600 new residents with access to a pathway within a 10-minute walk.
Broadway - Existing Conditions
Broadway - Existing Conditions

Preferred Alternative: Eastern Loop Alignment

The preferred alternative will would construct a multi-use pathway along the southern loop ramp and under the Federal Way overpass, connecting along the eastern side of Broadway Ave. A physical barrier would be placed between the pathway and roadway as it parallels Broadway Avenue. A new pedestrian crosswalk would be installed on Federal Way to provide access to the pathway.

Alternative 1 - Perspective Rendering
Alternative 1 - Perspective Rendering

Project Timeline

Please Note: Dates are tentative and subject to change.

  • Public outreach 1: October 2024
    • The public is encouraged to review the preliminary design plans and provide comments on their preferred alternative.
  • Select preferred alignment: November 2024
    • Public feedback will be carefully considered, and the final design option will be chosen based on community input and technical analysis.
  • Begin Final design: Winter 2024
    • The project team will finalize the plans, incorporating the selected alignment and any necessary adjustments.
  • Public outreach 2: Summer 2025
    • The public will have another opportunity to learn about the selected design, funding, impacts, and project benefits.
  • Complete Final Design: 2026  *we are here*
    • The project team will incorporate the findings of Public Outreach 2 into the design and prepare the project for bid and construction.
  • Anticipated construction: 2027
    • Construction is expected to begin, bringing the design to life.

Message Sent Successfully!

Message Failed To Send.

Send a Message to Planning

Thank you for your interest in the Planning division. Please fill out the form below and a representative will be in touch with you. If you are inquiring about a specific project, please include the record number or project address.